# Integrated Project Delivery
Integrated Project Delivery (IPD) is a collaborative project delivery method that aligns the interests of owner, architect, and contractor through a single multi-party agreement with shared risk and reward. IPD leverages early involvement of all key participants, BIM-enabled collaboration, and lean construction principles to optimize project outcomes, reduce waste, and deliver buildings that better serve their intended purpose.
---
## Table of Contents
- [IPD Principles](#ipd-principles)
- [Multi-Party Agreement](#multi-party-agreement)
- [Shared Risk and Reward](#shared-risk-and-reward)
- [Team Structure](#team-structure)
- [BIM Integration](#bim-integration)
- [Target Value Design](#target-value-design)
- [Lean Construction in IPD](#lean-construction-in-ipd)
- [Comparison with Other Methods](#comparison-with-other-methods)
- [Implementation Challenges](#implementation-challenges)
- [See Also](#see-also)
---
## IPD Principles
| Principle | Description |
|-----------|-------------|
| **Mutual Respect and Trust** | All parties treated as equal contributors |
| **Mutual Benefit and Reward** | Success shared; no party benefits at another's expense |
| **Collaborative Innovation** | Ideas evaluated on merit regardless of originator |
| **Early Goal Definition** | Project goals established collectively at inception |
| **Intensified Planning** | Greater effort in early phases reduces costly changes later |
| **Open Communication** | Transparent sharing of information, including financial data |
| **Technology Integration** | BIM as the shared design and coordination platform |
| **Organization and Leadership** | Collaborative decision-making through integrated team |
---
## Multi-Party Agreement
Unlike traditional two-party contracts, IPD uses a single agreement binding owner, architect, and builder:
| Feature | IPD Agreement | Traditional Contract |
|---------|--------------|---------------------|
| Parties | Owner + architect + builder (minimum) | Two-party (owner-architect, owner-contractor) |
| Liability | Limited liability among signatories; mutual waiver of claims | Full liability exposure between parties |
| Decision-making | Consensus through Project Management Team | Hierarchical; owner decides |
| Financial transparency | Open books; all parties share cost information | Closed books; each party protects margin |
| Early involvement | All parties from project inception | Sequential engagement |
### Standard IPD Contracts
| Contract | Source |
|----------|--------|
| **AIA C191** | Standard Form Multi-Party Agreement for IPD |
| **ConsensusDocs 300** | Standard Multi-Party Integrated Project Delivery Agreement |
| **CCDC 30** | Canadian IPD agreement |
| **Bespoke** | Many IPD projects use tailored agreements |
---
## Shared Risk and Reward
| Component | Description |
|-----------|-------------|
| **Cost of the Work** | Actual direct costs (reimbursed at cost) |
| **Overhead and Profit** | Fixed fee for each party's overhead and profit |
| **Risk Pool** | Portion of overhead/profit placed "at risk" against cost overrun |
| **Incentive Pool** | Savings below target cost shared among parties |
| **Target Cost** | Collaboratively developed budget; the shared financial goal |
### Financial Structure
| Scenario | Outcome |
|----------|---------|
| **Under target cost** | Savings distributed to all parties from incentive pool |
| **At target cost** | All parties receive full overhead and profit |
| **Over target (within risk pool)** | Overrun absorbed by risk pool; parties lose portion of profit |
| **Over target (beyond risk pool)** | Owner absorbs cost beyond risk pool (parties don't lose base fees) |
---
## Team Structure
| Level | Role | Composition |
|-------|------|-------------|
| **Project Management Team (PMT)** | Strategic decisions, financial approval | Senior representative from each signatory |
| **Project Implementation Team (PIT)** | Day-to-day design and construction management | Project managers, lead designers, superintendent |
| **Cluster Groups** | Specialist task teams | Design clusters, MEP cluster, envelope cluster |
| **Big Room** | Co-located collaborative workspace | Representatives from all parties working together |
### The Big Room
Co-location is a defining feature of IPD. Key participants work in a shared space for significant portions of the project, enabling:
- Real-time decision making
- Reduced communication lag
- Informal knowledge exchange
- Stronger team relationships
---
## BIM Integration
| IPD Phase | BIM Use |
|-----------|---------|
| **Conceptualization** | Shared model for option testing, energy analysis |
| **Criteria Design** | Coordinated multi-discipline BIM model |
| **Detailed Design** | Clash detection, construction sequencing |
| **Implementation Documents** | Fabrication-level models, coordination drawings |
| **Construction** | 4D scheduling, field coordination, quality control |
| **Closeout** | As-built model for facility management handover |
BIM is essential to IPD because it provides the shared platform for transparent, multi-party collaboration. See [[BIM Fundamentals and LOD]] for model development requirements.
---
## Target Value Design
Target Value Design (TVD) reverses the traditional cost estimation process:
| Traditional | TVD |
|------------|-----|
| Design first, estimate cost later | Set budget first, design to the budget |
| Cost is an outcome | Cost is a constraint/input |
| Value engineering after design | Value embedded during design |
| QS provides cost feedback periodically | Cost estimator embedded in design team continuously |
### TVD Process
1. Owner establishes allowable cost based on business case
2. Team sets target cost (typically 5–15% below allowable cost)
3. Design progresses with continuous cost tracking
4. If cost exceeds target, team redesigns rather than value-engineers
5. Savings below target cost are shared as incentive
---
## Lean Construction in IPD
| Lean Tool | Application in IPD |
|-----------|-------------------|
| **Last Planner System** | Pull-based scheduling with commitments from trade contractors |
| **Value Stream Mapping** | Identifying and eliminating waste in design and construction processes |
| **Set-Based Design** | Exploring multiple design options before converging late |
| **A3 Reporting** | Structured problem-solving on a single sheet |
| **Choosing by Advantages** | Transparent decision-making based on weighted advantages |
| **5S** | Workplace organization (Sort, Set, Shine, Standardize, Sustain) |
---
## Comparison with Other Methods
| Feature | IPD | Design-Bid-Build | Design-Build | CM at Risk |
|---------|-----|------------------|-------------|-----------|
| Team formation | All from start | Sequential | Designer + builder early | CM early, trades later |
| Risk allocation | Shared | Transferred | Shared (D-B team) | Shared (GMP) |
| Innovation incentive | High | Low | Medium | Medium |
| Cost transparency | Open books | Closed | Often closed | GMP with contingency |
| Change management | Collaborative | Adversarial | Negotiated | Negotiated |
| BIM requirement | Essential | Optional | Common | Common |
| Contract complexity | High | Low | Medium | Medium |
| Suitable project types | Complex, high-value | Simple, well-defined | Medium complexity | Medium-high complexity |
See also [[Design Build Delivery]], [[Construction Management at Risk]], [[Traditional Design Bid Build]].
---
## Implementation Challenges
| Challenge | Mitigation |
|-----------|-----------|
| Cultural change | Training, team building, IPD-experienced facilitator |
| Legal unfamiliarity | Specialist IPD legal advisors |
| Insurance complexity | Parties may need project-specific insurance |
| Open-book resistance | Build trust incrementally; third-party audit |
| Co-location cost | Phase co-location; use digital collaboration when remote |
| Team selection | Choose based on collaborative capability, not just price |
| Owner engagement | IPD requires active, engaged owner participation |
---
## See Also
- [[Design Build Delivery]]
- [[Construction Management at Risk]]
- [[Traditional Design Bid Build]]
- [[BIM Fundamentals and LOD]]
- [[RIBA Plan of Work]]
- [[Construction Project Planning]]
---
#ipd #integrated-project-delivery #collaborative #lean-construction #bim #target-value-design #professional-practice